On May 31, with the release of the last dispatching order and execution, the 500 kV Yetao substation was put into operation smoothly.
It is understood that the 500 kV Yetao substation is the 22nd 500 kV substation commissioned by Hebei South Network and the fourth 500 kV substation in the region. The project completed the feasibility study of the project in November 2015, and started construction in February 2017, which was managed by Hebei Power Supply Company.
During the construction of the project, Handan Power Supply Company organized the work plan of “Safety and Civilization Construction Overall Planningâ€, “Standardization Construction Management Outlineâ€, “Green Construction Management System†and “Engineering Construction Excellence Plan†to build an effective, scientific and rational project construction. Management system and security system. At the same time, it actively carried out territorial management and coordination work, strengthened communication with local government departments, and ensured that the project was constructed on schedule. Closely focusing on the working ideas of “intrinsic safety, green construction, striving for national excellenceâ€, mobilizing the subjective initiative of design, construction, supervision and other participating units, strengthening on-site safety control, taking measures such as hardening, sprinkling and dust reduction at construction sites To achieve the construction goal of “four sections and one environmental protection†to ensure efficient, safe and green development of the project.
In the current stage, the Yetao Substation will build 2 sets of 1000 MVA main transformers, 5 sets of 500 kV outlets and 6 sets of 220 kV outlets. The station adopts advanced, reliable, environmentally friendly and integrated intelligent equipment, and has advanced functions such as real-time automatic control of the power grid, intelligent adjustment, online analysis and decision-making and collaborative interaction, reaching the advanced level of the domestic mainstream intelligent substation. The smooth operation of the station will effectively alleviate the power supply pressure of the western Yunnan power grid and form a 500 kV ring network frame in the Luan area. The grid structure of the grid will be further strengthened, and the power supply capacity and intelligence level will be greatly improved. â€
Guangzhou Yunge Tianhong Electronic Technology Co., Ltd , https://www.e-cigarettesfactory.com